Switchboard & Fault Scenario Sizing Calculator

Generic 3-phase, phase-phase and phase-earth preliminary switchboard assessment
Handy Tools
← Back to Handy Tools
Preliminary engineering aid — not a formal fault study. This tool follows the newly supplied “Switchboard and Fault Scenario Sizing” workbook. It uses simplified lumped sequence-impedance calculations and the workbook’s direct multiplier for approximate peak current. Utility, transformer, motor and detailed inverter fault behaviour are not automatically modelled.

1. Source / Sequence Inputs

V
No.
kVA
A
kA RMS
kA RMS
%
%
%
× Isc
p.u.
p.u.
lag
V
The attached workbook applies 1.25 once to establish the fault-study kVA and then applies 1.25 again for switchboard kVA. These two factors are shown separately so the basis is visible. Its “Assumed X/R = 2.2” value is used directly as Ipk = Isc(3φ) × 2.2; this is presented as a workbook multiplier, not as a complete IEC peak-current derivation.

2. Project Notes

Calculated Fault Levels

3-phase Isc
kA RMS
Phase-phase
kA RMS
Phase-earth
kA RMS
Approx peak
kA, workbook multiplier
Aggregate inverter nameplate
CALC
Fault-study kVA basis
ASSUMPTION
3-phase fault current
Z1
Phase-phase fault current
Z1+Z2
Phase-neutral fault current
Z1+Z2+Z0
Phase-earth fault current
SAME BASIS
Approximate peak / asym value
NOT IEC PEAK
The workbook's peak calculation is simply 3-phase Isc × the entered multiplier. Formal IEC 60909 peak current uses a separate kappa relationship and network R/X data.

Preliminary Switchboard Basis

Switchboard power basis
ASSUMPTION
Calculated board current
Combined inverter rated current
NAMEPLATE
Board current ÷ inverter nameplate current
INFO
VERIFY DESIGN BASIS
No automatic standard switchboard size is selected. Final rated current, short-time withstand, peak withstand, form of separation, temperature rise, busbar system, protection, arc-fault requirements and assembly verification remain the switchboard manufacturer's / designer's responsibility.

Engineering Limitations

Sequence impedance: Z1, Z2 and Z0 must be on a consistent base. The simplified equations do not replace a network fault study.
Inverter contribution: grid-following/grid-forming inverter fault current is control- and time-dependent. Do not treat a nameplate kVA and a fixed impedance as universally representative without OEM confirmation.
Switchboard: verify the final assembly against the applicable AS/NZS 61439 requirements and project/network requirements.